Home » Project Information » Schedule

Construction Staging and Schedule


During the first stage of construction, which starts in early 2020, Markley Street (U.S. 202 South) will be restricted to one-way southbound between Elm Street and Main Street to provide sufficient space for crews to work safely.

During the current stage of construction, crews may be working weekdays from 7:00 AM to 4:00 PM on the northbound side of Markley Street. No additional lane closures on Markley Street are planned at this time.

Northbound Markley Street (U.S. 202 South) travelers will be detoured onto DeKalb Street (U.S. 202 North) starting at King Manor, at the northern approach of the Dannehower Bridge. PennDOT will modify the timing of traffic signals on DeKalb Street to enhance traffic flow during the Markley Street (U.S. 202 South) partial closure.

Markley Street detour map

 

PennDOT's goal is to minimize inconvenience to adjacent property owners, pedestrians, and motorists in the construction areas.

  • Pedestrian access will be maintained on at least one side of Markley Street (U.S. 202 South) at all times
  • A supplemental pedestrian detour route will be provided on Astor Street between Marshall Street and Main Street until pedestrian access is established on the new bridge over Stony Creek

Pedestrian access graphic

Night-time operations will be utilized during the installation of precast pavement panels to reconstruct the intersection of Main Street and Markley Street (U.S. 202 South). The night-time operation will start after the evening peak travel hours and be completed prior to the next morning's peak travel hours, thereby minimizing additional travel disruptions.

Existing ITS (Intelligent Transportation Systems) elements installed during the Section 520 project and connected to the PennDOT Traffic Management Center in King of Prussia, will monitor traffic flow and provide travel information to motorists on and approaching Markley Street (U.S. 202 South) and DeKalb Street (U.S. 202 North).


CONSTRUCTION STAGES

Stage 1A (Jan. 2020 - May 2021)

CONSTRUCTION COMPLETED

  • Reconstruct northbound Markley Street (U.S. 202 South) between Main Street and Elm Street

Stage 1B (May 2021 - Aug. 2022)

CONSTRUCTION COMPLETED

  • Reconstruct southbound Markley Street (U.S. 202 South) between Main Street and the Airy Street overpass

Stage 2A (Feb. 2022 - July 2022)

CONSTRUCTION COMPLETED

  • Reconstruct westbound Main Street between Barbadoes Street and Markley Street (U.S. 202 South)

Stage 2B (Feb. 2022 - July 2022)

CONSTRUCTION COMPLETED

  • Reconstruct westbound Main Street between Markley Street (U.S. 202 South) and Water Street
  • Reconstruct southbound Markley Street (U.S. 202 South) between the Airy Street overpass and Main Street

Stage 2C (July 2022 - Oct. 2022)

CONSTRUCTION COMPLETED

  • Reconstruct eastbound Main Street between Water Street and Main Street

Stage 2D (July 2022 - Oct. 2022)

CONSTRUCTION COMPLETED

  • Reconstruct eastbound Main Street between Markley Street (U.S. 202 South) and Barbadoes Street

Stage 2E (Sept. 2022 - Oct. 2022)

CONSTRUCTION COMPLETED

  • Reconstruct the center of Main Street between Water Street and Markley Street (U.S. 202 South)

Stage 3 (Nov. 2022 - Nov. 2022)

CONSTRUCTION COMPLETED

  • Reconstruct the median of Markley Street (U.S. 202 South) between Main Street and Ann Street

Stage 4 (Nov. 2022 - Dec. 2022)

CONSTRUCTION COMPLETED

  • Final paving of Markley Street (U.S. 202 South) between Marshall Street and Elm Street